KGHM S.A.
Copper smelter "Głogów"
KGHM Polska Miedź S.A is a world leader in copper production. Annually, the KGHM Group produces approximately 700 thousand tons of electrochemically refined copper. One of the KGHM branches is Huta Miedzi Głogów (HMG) – Copper Smelter Głogów. This plant is composed of two technological lines – HM Głogów I and HM Głogów II. We have realized the following projects:
Year 2017
-
Documentation and intelligent power supply and control systems for devices in the project “Installation for Calcining of Concentrates Cu in HMG I”.
-
Energy projects of five intelligent low voltage switchgears
-
Control systems for over 130 technological outlets
-
Operating software for 7 PLCs
-
Preparation of visualization systems for 4 operating panels
-
Operating software for over 150 units of Simocode ProV
-
Year 2013 – 2016
-
Documentation and intelligent power supply and control system for devices in the project “Modernization of Pyrometallurgy in the Copper smelter “Głogów”.
-
Energy projects of over 70 intelligent low voltage switchgears
-
Control systems for over 1500 technological outlets
-
Operating software for 120 PLCs
-
Preparation of visualization systems for over 60 operating panels
-
Operating software for over 2000 units of Simocode pro
Year 2013
-
Documentation and intelligent power supply and control system for devices in the project “Replacement of power supply for a P-23 Electric Furnace” within the scope of electric contactor boards.
-
Energy projects of over 12 intelligent low voltage switchgears
-
Control systems for over 600 technological outlets
-
Operating software for over 10 PLCs
-
Preparation of visualization systems for over 10 operating panels
-
Operating software for over 700 units of Simocode pro
Year 2012
-
Documentation and intelligent power supply and control system for devices in the project “Modernization of the slime filtration station in the E-4 object.”
-
Electric project and intelligent power supply and control system for devices in the project “Replacement of Section I and II of the switchgear 500V OST-22/6 in the P-24 department of Copper smelter Głogów II”.
-
Electric project for modernization of a switchgear and an intelligent power supply and control system for devices in the project “Development of an existing RGS4 switchgear in the installation of a lime-refining furnace in the P-4 department of copper smelter Głogów S.A.”
-
Electric project for modernization of a switchgear and an intelligent power supply and control system for devices in the project “P-5 Modernization of a switchgear 400/230V OST-4 in the P-5 department / Cast and Caissons Foundry”.
Year 2011
-
Documentation and intelligent power supply and control system for devices in the project “Replacement of the pump in the slime filtration station in the E-4 object”.
Year 2010
-
Documentation and intelligent power supply and control system for devices in the project “New pumps in the slime filtration station in the E-4 object.”
-
Documentation and intelligent power supply and control system for devices in the project “P-6 Modernization of the Sulfuric Acid Factory”.
-
Energy projects of 5 intelligent low voltage switchgears
-
Control systems for over 300 technological outlets
-
Operating software for 8 PLCs
-
Preparation of visualization systems for 5 operating panels
-
Operating software for over 400 pieces of Simocode pro
Year 2009
-
Documentation and intelligent power supply and control system for devices in the project “Installations for a steam conditioning station in the Steam Drying Plant in HM Głogów II”.
-
Documentation and intelligent power supply and control system for devices in the project “Modernization of the Sulfuric Acid Section P-26 in HM Głogów II”.
Year 2008
-
Documentation and intelligent power supply and control system for devices in the project “Replacement of switchgears 400V and 500V in the OSR-22 station”.
Year 2007
-
Documentation and intelligent power supply and control system for devices in the project “Construction of a new installation for the Dorr Settling Tank in HM Głogów II”.
-
Electric project and intelligent power supply and control system for devices in the project “Replacement of Section I and II of the switchgear 400V OST-22/6 in the P-24 department of Huta Miedzi Głogów II”.
-
Electric project of a switchgear and intelligent power supply and control system for devices in the project “P-5 Modernization of switchgear 400/230V OST-4 in the P-5 department / Cast and Caissons Foundry”.
Year 2006
-
Documentation and intelligent power supply and control system for devices in the project “Construction of a new installation of an electrostatic precipitator in the Department of Sulfuric Acid P-6 in HM Głogów I”.